Frequently Asked Questions 1: Time Scale?

Question 1: What is the Time Scale?

Answer: The intended time line is as follows
  • June – November 2009: Technical feasibility study .
    Identify and make initial approaches to potential funding, development and technology partners.
    Seek opportunities for development funding.
    Ongoing engagement with stakeholders
  • 2010 to 2013: If the 1st Technical Feasibility study allows, move to a Full Feasibility Study-
    Full range of environmental, social and economic impact studies undertaken
    Technology and development funding streams identified and secured. Contractors / Developers identified and contracts drawn up.
    Design and outline planning for all project aspects
    Project funding streams identified and agreed
    Extensive stakeholder engagement
    Resource, supply chain identification
    New regional branding strategy explored and developed
    Grid connection agreement
    Crown Estate and relevant land owner provisional agreements
    Provisional development vehicle and structure formalised
    Connectivity issues identified and resolved
    Special interest stakeholder groups formed to feed into development
  • 2013 to 2014:  If previous stage is positive go to Planning
    Planning and consents sought. CPO orders. Agreements signed
    Community and Interest Groups feed in
    Supply chain geared up
    Recruitment of necessary construction personnel
  • 2014 to 2016: Construction
    Project build
    Connectivity links made
    Regional branding and promotion
  • 2016 to 2017: Commissioning

0 Comments:

Post a Comment

<< Home

 

Copyright © 2011 Solway Energy Gateway Ltd . All rights reserved. Disclaimer | Privacy Statement
Registered office Queens Barn, Welton, Cumbria, CA57HG
Company Registration Number: 06926895
Powered by iEditor