Frequently Asked Questions 1: Time Scale?
Question 1: What is the Time Scale?
Answer: The intended time line is as follows
Answer: The intended time line is as follows
- June – November 2009: Technical feasibility study .
Identify and make initial approaches to potential funding, development and technology partners.
Seek opportunities for development funding.
Ongoing engagement with stakeholders
- 2010 to 2013: If the 1st Technical Feasibility study allows, move to a Full Feasibility Study-
Full range of environmental, social and economic impact studies undertaken
Technology and development funding streams identified and secured. Contractors / Developers identified and contracts drawn up.
Design and outline planning for all project aspects
Project funding streams identified and agreed
Extensive stakeholder engagement
Resource, supply chain identification
New regional branding strategy explored and developed
Grid connection agreement
Crown Estate and relevant land owner provisional agreements
Provisional development vehicle and structure formalised
Connectivity issues identified and resolved
Special interest stakeholder groups formed to feed into development
- 2013 to 2014: If previous stage is positive go to Planning
Planning and consents sought. CPO orders. Agreements signed
Community and Interest Groups feed in
Supply chain geared up
Recruitment of necessary construction personnel
- 2014 to 2016: Construction
Project build
Connectivity links made
Regional branding and promotion
- 2016 to 2017: Commissioning